A kitchen renovation in a Vancouver winter works well, because almost all of it happens indoors and the cabinets are built off site while your old kitchen keeps working. What winter changes is the edges of the job: deliveries in the rain, nowhere dry to stage outside, slower drying for the wet trades, a closed-up house, and holiday closures that move more dates than the weather does. Plan for those and a winter kitchen is no slower than a summer one. Here is how each one plays out.
The longest stretch of a custom kitchen is manufacturing, and it does not happen in your house. Our standard is about 4 weeks to build the cabinetry once the design is signed and the room is measured, and during those weeks you are still cooking in your old kitchen. Everything after that happens inside: removal, rough-in by the trades, drywall, install and counters. Rain does not stop any of it. The parts of a renovation that depend on the weather are few, and they can be named and planned in advance.
Our cabinets arrive pre-assembled, which means finished boxes, doors and drawer fronts travelling from the truck to your door. In a dry month that path hardly matters. In a wet one it does. Cabinet boxes and painted fronts should not sit in the rain, on a wet driveway, or in a cold garage or carport for days. Plan a heated room inside the house to stage them, clear a path to it, and lay floor protection from the door through to the kitchen. A covered entry helps, and so does booking the delivery for a time someone is home. Counters, appliances and the old cabinets going out use the same path, so protect it once and keep it protected.
Several trades in a kitchen work with materials that dry or cure: drywall compound, primer and paint, tile adhesive and grout, and some floor finishes. Cold, damp air slows all of them. Keep the heat on in the house through the whole project, even while the kitchen is open, and keep air moving where the trades ask for it. Each trade can tell you its own drying times, and they are worth asking for, because paint over compound that has not dried, or cabinets set on a floor that has not cured, shows up later. If an outside wall is being opened, for a new window or for a range hood duct that vents through the wall, that is the one piece of work that watches the forecast. The trade will pick a dry day for it.
In summer a renovation airs out through open windows. In winter the house is closed, so dust from removal and drywall sanding has fewer ways out. Ask your contractor about dust barriers between the kitchen and the rest of the house. If you have a forced-air furnace, the vents near the kitchen are worth covering during removal and sanding, and the filter is worth changing once the dusty work is done. Set up the temporary kitchen in a warm, well-lit room away from the work, a dining room rather than a garage, because the weeks without a sink feel longer when the days are short.
From mid-December into the new year, many suppliers, counter fabricators and trades take time off, and their closures do not always line up. Counters are templated after the cabinets are in and fabricated on the fabricator's schedule, so a counter that would take a week or two in October can wait longer over the holidays. Appliance deliveries can slow too. Ask every party for their closure dates before you lock a schedule, and put them all on one calendar. That calendar matters more than any forecast.
The simplest winter plan works with the holidays rather than against them. If you want your old kitchen for a holiday dinner, plan the design so the old kitchen comes out after it, and let the manufacturing weeks run while you still cook at home. If you would rather not have the install split around the closures, aim for it to land before mid-December or after the new year, and work the design and manufacturing weeks back from that date. Either way the order is the same: design and measurements, about 4 weeks of manufacturing, a few days of removal and trades, a few days of install, then counters. Winter only changes which week each step lands in.
For the week-by-week view of the whole project, read living through a kitchen renovation, week by week, and for the steps before sign-off, how long a custom kitchen takes. Each stage is laid out on our process page. The Vancouver Kitchen Cost Calculator gives you a rough range, and when you want your dates worked out against the holidays, book a free consultation.